Case study:
DePuy
Logistics improvement project
Context
Failure to raise productivity and responsiveness were beginning to pose a risk to key customer relationships and action was urgently required. Project management expertise was an essential prerequisite coupled with knowledge and understanding of Lean thinking and Change management.
blackswan responsibilities
- Operations assessment, project management and change management
- Planning and communication using MS Project & Visio
- Management of cross-functional project teams
- Technical support
- Manage stakeholder relationships
- Project implementation
Objectives
- Improve productivity and service key performance indicators (KPI’s) in compliance with GMP and regulatory guidelines
- SMED capability along side TOC principles
- Transfer knowledge and build a sustainable continuous improvement programme (CIP)
- Improve staff engagement with process innovation plans, manage change
- Find and remove process bottlenecks, lift productivity
Achievements
- Productivity increased by 30%
- Improved Supply chain response – zero back orders achieved (i.e., shifted bottleneck to the market)
- Lean knowledge transfer, SMED, VSM & TOC – staff development
- Ongoing improvement programme established
Project ROI of 7 to 1

Latest News
-
blackswan Newcastle office moves
01 July 2010
Blackswan have today moved to the significantly larger office complex
-
Darrell Mann joins blackswan
19 May 2010
Darrell Mann joins blackswan to bring People, Process and Innovation offering to the market
CEO update
-
M Duffy CEO charity work
01 April 2010
M Duffy CEO pays a visit to Percy Hedley school.