Case study:
Cuisine de France 

Project goal - increase production OEE / output

Phase 1 Project

Lean project - production lines

  • Develop current capacity baseline numbers (OEE rated at 43%)
  • Carry out introductory Lean training with supervisors (particular emphasis on Overall Equipment Effectiveness - OEE & Short Term Interval Management- STIM)
  • Implement Line Balancing
  • Standardise line targets and output, live KPI measurement
  • Develop visual control boards to manage production flow
  • Implement STIM target variance management
  • Develop Lean supervisory tools - OEE Log, Downtime Log, First hour efficiency log & an operating training / flexibility matrix.

Phase 2 Project

Supervisor Development

  • Define baseline performance benchmark
  • Evaluate 8 front line supervisors against this spec
  • Develop personal development timeline plan to bridge identified gaps for each supervisor (Action Orientation, Problem Solving, Teamwork, Performance Management, Communication)
  • Carry out training and mentoring on an individual basis
  • Particular emphasis on short term interval management (cases per minute), first hour efficiency, downtime analysis & continuous improvement

Project Achievements

Financial

  • Primary project goal was to Increase OEE
  • Starting Position - 43%
  • Ending Position - 66% (max achievement was 72%)
  • Increase of 23% - or a financial increase of €837K, Year 1 (based on 1% OEE valued at 36.4K)

Non Financial

  • The foundations for world-class manufacturing are in place and being utilised by the supervisors
  • KPI's identified with supporting Visual Display management in place
  • Supervisor Role & Responsibilities Defined
  • Supervisor Competencies defined and graduated for development
  • Supervisor Training Versatility chart developed
  • Focus of Supervisor work changed to Performance and Availability
  • OEE Dashboard created
  • 1st Hour Efficiency Report created
  • Downtime Log created and implemented
  • Line Operator performance competencies and skills identified
  • Line Operator Training Versatility chart developed
  • Number of production teams decreased by 1 (5 to 4) while producing 6% more than previous year

Project ROI of 18 to 1

Cuisine de France